Breadcrumb
Get Permit to Start Constriction Work
This service enables you to get the municipality's approval to start construction works at the site.
You are starting service as:
Personal account
gup-business-account-label
Required documents
- Contractor and consultant undertaking
- Electricity maps
- Color undertaking
- Mark delivery form
-
Service category and fees Show Hide
Application feesThe beneficiary pays 1 OMR when submitting the application.
1
Steps
-
1
Submitting the application
-
2
Accepting the application
-
3
Setting inspection date
-
4
Performing technical inspection
-
5
Insurance payment
-
6
Receiving the permit
Special conditions
- Follow-up reports must be submitted by the consultant before starting a new phase of construction.
- There must be a supervising consultant for buildings over 10,000 OMR in value, or buildings with more than one floor no matter the value.